Data center moratoriums and pauses

The Baldwin Group
|
Updated: October 29, 2026
|
19 minute read

Driven in large part by the AI boom, demand for data centers has ballooned in recent years, with project viability often framed in terms of chips, power, and capital availability. But since the outset of 2026, community consent and regulatory constraints have moved from rare to routine, challenging project feasibility in ways that chips, power, and capital can’t.

Across the country, local governments are moving faster than state or federal policy on data center development. Some officials argue the pace of buildout has outrun the grid capacity, water supply, and community tolerance needed to support it. Developers and the investors behind them argue that abrupt regulatory pauses, even temporary ones, do more damage to a jurisdiction’s investment case than the underlying growth ever did.

Pauses and moratoriums on new applications don’t just slow data center growth. They stop the clock on financing assumptions built around a construction timeline. For owners, developers, and operators, that raises a harder question than which side is right: what happens financially and contractually the moment a pause is filed, regardless of the outcome?

From a risk and insurance perspective, a regulatory pause doesn’t need to become permanent to force a builder’s risk extension, test a delay in start-up (DSU) trigger, or strain contractual obligations nobody modeled for. Those consequences start the day a board votes to advance a proposal, not the day it takes effect.

Tracking these regulatory shifts has become as critical to project viability as tracking power availability or capital costs. Closing that gap takes more than legal compliance. It takes communication and education that bridge developer interests and community concerns, so new standards get built with multiple stakeholders’ needs in mind, not around them. The Baldwin Group works with owners, developers, and investors navigating exactly this shift, translating regulatory uncertainty into terms capital and coverage can actually price.

Data center projects by year (Jan – Jul window)

Federal, state, and local governments are moving at different speeds on data center regulation, and don’t always land on the same answer. For owners and developers, tracking how these actions develop, and where they ultimately land, is what shapes a project’s regulatory exposure.

Federal opinion about data center development is sharply divided, with the divide breaking along familiar party lines. Progressive lawmakers argue a federal pause is necessary to protect grid reliability, contain consumer utility rates, and set uniform safety standards before buildout outpaces oversight. Conservative lawmakers oppose a federal pause outright, framing it as economic overreach that would cede a technology race the U.S. is still positioned to win.

Notably, that federal standoff has produced no binding action. The real activity, and the real exposure, is happening at the local and state levels, where individual boards and councils control zoning, permitting, and the pace of application review directly.

Opposition has become more local and project-specific, targeting permitting, infrastructure, and individual policy decisions as scrutiny expanded across most states. Concerns over water use, energy consumption, noise, and utility rates have turned permission to operate into a fourth critical input for AI infrastructure, alongside chips, power, and capital.

  • More than 300 local moratoriums2 and bans on data center development are now in place nationwide.
  • Moratorium activity rose from roughly 1% of data center decisions3 in early 2025 to 28% in 2026, with 313 measures reaching local governments across 138 jurisdictions.
  • Local opposition delayed or rejected 75 AI data center projects worth $130B in Q1 2026 alone4. Another 45 projects worth $68B were disrupted in Q2 20265, holding disruption at that elevated pace.
  • Filings ran 29% ahead6 of last year through July 2026, and the industry’s footprint expanded from 13 states to 19. Local governments moved even faster: data center matters climbed from 0.11% to 0.30% of all local decisions over the same stretch.
  • Moratoriums tend to follow the same pattern: pause, then rewrite the code. 85% of moratorium actions7 surface as zoning code changes, and moratorium language now appears in 43% of all code modifications.

Local moratoriums are concentrated in the Midwest and South, clustered around regions experiencing the fastest infrastructure growth. Loudoun County, Virginia, hasn’t enacted a moratorium. But the mechanics playing out there—application pauses, financing timelines colliding with regulatory review—are the same mechanics driving exposure in states and local jurisdictions across the country.

Once a jurisdiction goes down the route of pausing one specific use, it becomes more acceptable. It becomes a lot easier for local jurisdictions to arbitrarily enact moratoriums.
– Bill Junda, PE – President, Gordon

Jurisdictions aren’t drafting these frameworks in isolation. Model ordinances and planning guides circulate through national associations8 and county commissions, giving localities templates to adopt a detailed regulatory framework with less overhead. Once one county’s approach becomes the reference point for the next, adoption compounds, which is a large part of why moratorium activity has moved from rare to routine in under two years.

On September 16, 2026, the Loudoun County Board of Supervisors advanced a twelve-month pause on new legislative applications, rezonings and special exceptions for data centers. Known as “Data Center Alley,” Loudoun County is home to more than 250 data centers10, with at least two dozen more in the pipeline, the largest concentration in the country.

Loudoun’s data center density is exactly why its regulatory fight has become a national bellwether. The facilities generated11 $1.2B in property tax revenue in fiscal year 2026, 39% of the county’s total budget, with fiscal year 2027 projected at $1.3B. Supporters point to that revenue as the foundation of the county’s low residential tax rate. Opponents point to noise, water and grid strain, and the pace of construction relative to the infrastructure meant to support it.

The board voted 7-1-112 to direct staff toward a final resolution, due October 20, with a proposed retroactive effective date of September 15. A second, separate track, pursued by Supervisors Juli Briskman and Laura TeKrony, sought to end grandfathered status for the 15 data center applications13 still under review from before the county’s 2025 by-right rules took effect, representing 30 buildings and roughly 10.5 million square feet of proposed development.

That track stalled at the board’s October 6 meeting.14 County staff estimated that revoking grandfathered status would likely trigger developer litigation, with potential county liability of $45M to $60M. County Attorney Leo Rogers also delivered a legal opinion to the board, though its contents remain attorney-client privileged. Facing that exposure, Briskman and TeKrony scaled back their proposal to a roughly $200,000 third-party audit, aimed at determining whether any of the 15 applications had already lost vested-rights or grandfathered status, rather than revoking that status outright. Supervisor Matt Letourneau opposed even the audit, calling it an implicit vote of no confidence in county staff’s own review process. The board tabled the audit motion 7-2, effectively ending the grandfathering push for now. A related motion from Supervisor Koran Saines15 is scheduled for the board’s October 20 meeting, the same date set for the pause’s final vote.

Supervisor Michael Turner’s proposed 500-foot residential setback16 and 45 dB noise cap remain in drafting as part of the county’s Phase 2 standards, not yet adopted. And the pause itself binds only new applications. Already-approved and grandfathered by-right projects continue on schedule, so the immediate exposure sits with the unfiled pipeline, not the built base.

This is a pause, not a moratorium, and the distinction carries meaningful legal implications17. County Attorney Leo Rogers has told the board he doesn’t believe it has authority to impose an outright moratorium.

Virginia’s Dillon Rule limits localities to powers the General Assembly has granted, and a 1975 Virginia Supreme Court ruling struck down Fairfax County’s attempt to freeze site plan and subdivision approvals outright. Rogers said courts have recognized only narrow exceptions, such as a temporary restriction tied to an identifiable public emergency, and is consulting other Virginia localities weighing similar measures before returning with a full legal analysis.

That constraint is shaping the board’s approach directly. Supervisor Laura TeKrony, who backed the measure over grid and community strain she called “at a breaking point,” argued a pause could hold up if tied to something specific, such as completing the county’s data center standards or an electrical infrastructure plan. The twelve-month cap and the narrow scope to new filings are the board’s attempt to thread that needle.

A regulatory pause creates real uncertainty, and that uncertainty also actualizes into a specific chain of financial and coverage consequences. Tracing that chain is critical because each link determines who absorbs the cost, and when.

A pause on new applications pushes a project’s construction timeline past the window its financing and insurance were built around. That slippage can force a builder’s risk policy into a mid-term extension, typically repriced at renewal, and priced against how long the project might actually sit in limbo, not how long the board’s pause is nominally scheduled to last.

The same delay tests DSU coverage, which compensates for lost revenue when a project’s completion slips past its expected date. DSU policies are typically built around delay caused by a covered peril: a fire, a storm, an equipment failure. A delay caused by a legislative pause may not cleanly fit that definition, and that ambiguity often doesn’t get resolved until a claim forces it.

Idle asset exposure sits underneath both. Land already acquired and infrastructure partially in the ground sit through the pause window, with coverage boundaries that were never written with this scenario in mind. The capital response follows directly: developers either extend an equity bridge to cover the gap or renegotiate debt covenants tied to milestones the pause has made unreachable on schedule.

A couple of consequences tend to follow immediately. Carrying costs rise as the pause extends financing assumptions past their original window, and every month of delay is a month of debt service and land costs with no offsetting revenue. Where construction milestones are covenant-linked, a missed date can become more than a scheduling problem: it’s a contractual default exposure, and lenders may not treat a regulatory pause as rationale for leniency.

Any jurisdiction that has the ability to enact a moratorium or a pause is definitely overly scrutinized now by anyone who is looking to invest capital.
– Bill Junda, PE – President, Gordon

The exposure doesn’t land the same way on every party. For example:

  • Developers and landowners absorb the direct cost: carrying costs, default risk, and the day-to-day decision of whether to hold a stalled application or walk.
  • Lenders face covenant triggers tied to disrupted timelines and decide whether a missed milestone becomes a technical default or a renegotiated term.
  • Underwriters and reinsurers are repricing DSU and builder’s risk against an undefined regulatory-delay boundary and a loss history that doesn’t exist yet, making today’s pricing as much judgment as data.
  • Hyperscaler tenants, the cloud and AI companies leasing capacity in facilities still under construction, carry a different exposure: SLA penalty risk if a leased facility’s completion date slips, regardless of who caused the delay.

None of this exposure is fixed once a pause is filed. Often, what determines whether a developer, lender, or underwriter absorbs the cost or gets ahead of it comes down to how the contracts and coverage were written before the pause ever hit.

Insurers have limited loss history for delay caused by regulatory action, as distinct from delay caused by a covered peril. That’s not a data problem insurers can quickly fix. It exists because policy-driven pauses at this scale are new, and most DSU language in the market today doesn’t clearly define where a covered-peril delay ends and a regulatory delay begins. Underwriters aren’t pricing that gap away. Instead, they’re pricing around it, which makes the ambiguity itself a cost, whether or not a claim ever tests it.

As project scale has expanded, a less discussed reality has emerged: the insurance market isn’t expanding as quickly. Average insured project values have surged18 from roughly $150M five years ago to about $3B today. At the largest end of the scale, campuses running into the tens of billions of dollars, there simply isn’t sufficient capacity in the market to insure them to full value.

No single insurer can absorb that scale alone: hyperscale projects increasingly rely on co-insurance arrangements, where multiple insurers each take a slice of the total limit, and even the largest dedicated capacity programs in the market may fall short of covering a flagship campus in full. That gap isn’t a temporary pricing problem. It’s structural, and it’s the backdrop against which the DSU ambiguity and idle asset exposure are playing out.

Developers moving to frontier markets in response to heightened regulatory actions may obtain land and power more easily and with fewer community constraints, but there’s a significant tradeoff. Many of these regions carry higher tornado, hail, and wind risk, and weather-related losses are now the leading driver of loss in data center builder’s risk portfolios.

Clustering campuses in the same region compounds the risks, and insurers are watching aggregation risk closely, since one severe event could hit several sites at once. The market hasn’t absorbed a truly catastrophic hyperscale loss yet. When it does, underwriting on concentrated regions will move fast.

The developers and investors who get ahead of the next pause are the ones acting now, not the ones reacting once regulatory action lands.

Build the welcome before you file. That means having conversations and making your commitments on water, power, and noise before the application goes in, and shaping a unique community benefits agreement around residents’ priorities, not a standard template. Treated as a prerequisite to filing rather than a response to opposition, that work is how a project earns its place as a neighbor, not just a taxpayer.
– Sandra Hagen Solin, Founder/CEO, Capitol Solutions
  • Site selection: Screen for moratorium risk upfront. Weigh pending legislation and political initiatives alongside the standard zoning and permitting checklist, since that same regulatory posture is already shaping how insurers price builder’s risk and DSU at placement.
  • Vested-rights documentation: Build the record as it’s created, not after it’s challenged. Securing key permits early and documenting reliance expenditures strengthens a vested-rights argument if a jurisdiction later moves to pause or revoke that status, and gives a developer the same evidence a DSU claim would need.
  • Community benefit commitments: Budget for them as a capital line, not a public affairs afterthought. Workforce and infrastructure commitments are increasingly the price of admission in jurisdictions weighing a pause, and cost less upfront than a mid-construction covenant renegotiation. Shaped before filing rather than negotiated under pressure, they do far more to prevent a pause than to resolve one.
  • Public education and proactive positioning: Publishing plain data on resource use, tax contributions, and job creation shapes the debate while it’s still open, rather than responding to opposition that’s already hardened.
  • Litigation tracking: Watch how courts define the limits of local pause authority. Each ruling narrows the regulatory-delay ambiguity DSU underwriters are pricing around today.
  • Contractual and coverage alignment: It may be worth reviewing whether covenant language and DSU or builder’s risk terms adequately anticipate regulatory-pause delay, ideally as part of a standing review ahead of each renewal cycle rather than after a claim raises the question.
  • Coordinated strategy: The strategies above are most effective when executed in coordination. Moratoria now intersect permitting, utility regulation, environmental review, and community engagement, so when legal, land-use, and coverage teams work in silos, a covenant can get drafted, or a renewal negotiated, without anyone flagging that the underlying zoning risk—or the community sentiment driving it—had shifted.

Coordinating across legal, land-use, and coverage functions is where a specialized advisory partnership with The Baldwin Group adds the most value, turning regulatory shifts into coverage and covenant language a developer can act on, not just react to.

For a very long time, data centers operated in the background and did not publicize their investment in the community and public education. The money they generate for localities tends to significantly lower property taxes for the average homeowner. They provide good jobs. They use a lot less resources than what’s being said about them in the media.
– Bill Junda, PE – President, Gordon

Every jurisdiction weighing a pause is running the same argument. Residents want time for infrastructure and zoning standards to catch up with a pace of construction that’s outrun grid capacity, water supply, and community tolerance in places like Loudoun. Developers argue the mechanism itself, not just how it’s used this time, is the real risk. Once a board demonstrates it can freeze applications on short notice, that capability doesn’t disappear when the pause expires.

Both arguments have merits that hold up on their own terms, and neither resolves the other. Researchers tracking this fight nationally19 point to a gap both sides tend to skip: a pause buys time, but time alone doesn’t produce better regulation. A pause only works if it’s paired with real data-gathering, transparency, and collaboration among legislators, industry, and residents, otherwise it just delays the same fight.

Chesapeake offers one version20 of that overlap, an eight-month pause tied to a finite condition, adopting updated zoning regulations, rather than an open-ended freeze. It reached that exit on schedule but landed on a permanent standard ending by-right development entirely, not a return to prior rules.

A bounded pause gives developers a stated endpoint instead of open-ended limbo. However, it doesn’t guarantee what’s waiting on the other side is any less restrictive.

A jurisdiction puts a durable standard in writing, a sunset clause, a defined completion condition, a limit on reuse, and developers get something concrete enough to tell an investor the regulatory risk is bounded. In exchange, developers have the option to move first, offering guaranteed setbacks, emissions controls, or noise limits before a board reaches for a pause to get the same result.

Neither side has to concede the underlying argument. They just have to agree the current default, uncertainty with no defined edges, serves nobody’s interests.

The developers who come out ahead aren’t defending a filing after opposition has hardened. They moved first, long before any board had a reason to vote, which is exactly the point. By the time a pause is even on the table, the question isn’t whether you did outreach. It’s whether you did it early enough to never need it.
– Sandra Hagen Solin, Founder/CEO, Capitol Solutions

The capital and coverage cost of a regulatory pause doesn’t wait for a final vote. It’s already showing up in how builder’s risk gets repriced, how DSU claims get contested, and how lenders read covenant language, in Loudoun and across the more than 300 jurisdictions running a similar experiment nationwide.

Few stakeholders fully grasp how far this exposure reaches. Developers and investors often underestimate how construction risk, delay exposure, and regulatory ambiguity compound against each other well before a facility is built or blocked.

The Baldwin Group helps close that gap, identifying specialized coverage solutions and serving as a risk advisor across the full project life cycle, from site selection through operation. Structured strategically, insurance becomes more than a safeguard. It becomes a tool that stabilizes returns and keeps financing intact as the regulatory landscape shifts county by county.

In Loudoun County, Virginia, the county attorney has told the board he doesn’t believe it has authority to impose an outright moratorium. Virginia’s Dillon Rule limits localities to powers the General Assembly has granted. So, the board advanced a twelve-month pause on new applications, which is narrower in scope. The distinction carries meaningful legal implications.

More than 300 local moratoriums and bans are now in place nationwide. Moratorium activity rose from roughly 1% of data center decisions in early 2025 to 28% in 2026. Local opposition also delayed or rejected 75 AI data center projects worth $130B in Q1 2026 alone.

They start the day a board votes to advance a proposal, not the day it takes effect. A pause doesn’t need to become permanent to force a builder’s risk extension, test a delay in start-up (DSU) trigger, or strain contractual obligations nobody modeled for.

A pause can push a project’s timeline past the window its financing and insurance were built around. That can force a builder’s risk policy into a mid-term extension, typically repriced at renewal. DSU policies are typically built around delay caused by a covered peril, such as a fire, a storm, or an equipment failure. A delay caused by a legislative pause may not cleanly fit that definition, and that ambiguity often doesn’t get resolved until a claim forces it.

The exposure doesn’t land the same way on every party:

  • Developers and landowners absorb the direct cost: carrying costs, default risk, and the decision of whether to hold a stalled application or walk.
  • Lenders face covenant triggers tied to disrupted timelines.
  • Underwriters and reinsurers are repricing DSU and builder’s risk against an undefined regulatory-delay boundary.
  • Hyperscaler tenants carry SLA penalty risk if a leased facility’s completion date slips, regardless of who caused the delay.

Developers may obtain land and power more easily and with fewer community constraints. Many of these regions, though, carry higher tornado, hail, and wind risk, and weather-related losses are now the leading driver of loss in data center builder’s risk portfolios. Clustering campuses in one region also compounds aggregation risk, since one severe event could hit several sites at once.

It is generally recommended to act immediately, not after regulatory action lands. Consider these strategic actions:

  • Screen sites for moratorium risk upfront.
  • Document vested rights as the record is created.
  • Budget for community benefit commitments as a capital line.
  • Publish plain data on resource use, tax contributions, and job creation.
  • Track litigation on the limits of local pause authority.
  • Review whether covenant language and DSU or builder’s risk terms anticipate regulatory-pause delay, ideally ahead of each renewal cycle.
  • Coordinate legal, land-use, and coverage teams so shifts in zoning risk or community sentiment get flagged.

Coordinating across those functions is where an advisory partnership with The Baldwin Group adds the most value.

  1. Shovels, “Data Center Moratoriums Went From Rare to Routine in a Year,” September 22, 2026, Ruoji Tang ↩︎
  2. Semianalysis, “Everyone Says Datacenter Moratoriums Are Killing the US Buildout. We disagree,” September 15, 2026, Maya Barkin, Reyk Knuhtsen, Jeremie Eliahou Ontiveros, and Dylan Patel ↩︎
  3. Shovels, “Data Center Moratoriums Went From Rare to Routine in a Year,” September 22, 2026, Ruoji Tang ↩︎
  4. Data Center Watch, “Q1 2026: Data Center Watch Report,” January – March 2026 ↩︎
  5. Data Center Watch, “Q1 2026: Data Center Watch Report,” January – March 2026 ↩︎
  6. Shovels, “Data Center Moratoriums Went From Rare to Routine in a Year,” September 22, 2026, Ruoji Tang ↩︎
  7. Shovels, “Data Center Moratoriums Went From Rare to Routine in a Year,” September 22, 2026, Ruoji Tang ↩︎
  8. Shovels, “Data Center Moratoriums Went From Rare to Routine in a Year,” September 22, 2026, Ruoji Tang ↩︎
  9. Datacenterbans.com, “Data Center Moratoriums, Tracking state-level data center legislation across the United States” ↩︎
  10. The New York Times, “A County Got Rich From Data Centers. Some Question ‘At What Cost’, August 19, 2026, Cecilia Kang ↩︎
  11. Loudoun County Government, “Data Centers: Tax Revenues & County Budget” ↩︎
  12. MGRID.org, “Loudoun County Voted 7-1-1 to Draft a Data Center Pause, Not to Start One,“ October 5, 2026 ↩︎
  13. Loudoun Now, “Loudoun Board Prepares for Big Data Center Changes as Lawsuit Threats Loom,” September 3, 2026, Josh Janney ↩︎
  14. Loudoun County Board of Supervisors, Business Meeting Agenda, October 6, 2026 ↩︎
  15. DC News Now, “Loudoun delays data center review as county warns of up to $60M in legal risk” October 6, 2026, Ben Dennis ↩︎
  16. The Washington Times, “Loudoun County Board of Supervisors to draft resolution pausing data center applications for a year,” September 16, 2026, Brad Matthews ↩︎
  17. Virginia Business, “Loudoun supervisors mull data center moratorium,” July 27, 2026, Josh Janney ↩︎
  18. Risk & Insurance, “Data Center Insurance Capacity Strained as Average Project Values Surge From $150 Million to $3 Billion,” May 27, 2026, R&I Editorial Team ↩︎
  19. Brookings, “Data center moratoriums are not a substitute for oversight,” July 28, 2026, Nicol Turner Lee and Darrell M. West ↩︎
  20. Chesapeake Virginia, “Data Center Ordinance and Policy” ↩︎
RELATED INSIGHTS

Stay one step ahead

Discover expert insights to help you understand industry trends and emerging risks, so you can act proactively to better protect your business.

Collectibles
Wine collection insurance: how to protect valuable bottles and cellars
Protecting a fine wine collection comes down to three things: the right storage conditions, an up-to-date inventory, and insurance built…
Medicare
Medicare annual enrollment 2027: Key dates and what to review
The Medicare Annual Enrollment Period is an important opportunity to review your Medicare coverage and make sure it still fits…
Home and Property
How Much Does Home Insurance Cost? 
Home insurance premiums can differ substantially between properties, even within the same neighborhood. Location, rebuilding costs, property condition and coverage…
Home and Property
Understanding Hurricane Deductibles: Protecting Your Home During Storm Season 
Hurricanes can cause extensive damage to homes, from torn-off roofs and broken windows to major structural repairs. While homeowners insurance…
Family Protection
Travel security for high-net-worth families
Travel security is the set of planning steps and daily habits that help protect you, your family, your personal information,…